Braddan Bridge Nearing Completion
The road will remain one way from Braddan Church roundabout towards Quarterbridge over the weekend and into next week
While plans to asphalt at the Jubilee Oak yesterday were thwarted by the damp conditions, it is anticipated that the last section of surfacing will take place.
The Braddan Road/Peel Road junction will stay closed overnight to allow the asphalt to cool and harden.
At about 8am tomorrow (Saturday) the Braddan Road/Peel Road junction will reopen. The road will remain one way from Braddan Church roundabout towards Quarterbridge over the weekend and into next week. The planned weekend closure of the Jubilee Oak roundabout will not be required.
It is planned to complete line marking next week. The current temporary traffic order expires at the end of the working day on Wednesday (31 January).
As line marking needs a relatively dry surface to be successfully applied it may be that the temporary order may need to be slightly extended if we have unsuitable weather.
A decision about this will be made next week when we know how the lining work is progressing.